OCTOBER TERM, 2001
Syllabus
FRANCONIA ASSOCIATES ET AL.
v. UNITED STATES
CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE FEDERAL
CIRCUIT
No. 01-455. Argued April 15, 2002-Decided June 10,2002*
Under §§ 515 and 521 of the Housing Act of 1949, the Farmers
Home Administration (FmHA) makes direct loans to private, nonprofit
entities to develop and/or construct rural housing for the elderly
and low- or middle-income individuals and families. Petitioners are
property owners who entered into such loans before December 21,
1979. The promissory notes petitioners executed authorized
"[p]repaymen[t] of scheduled installments, or any portion thereof,
... at any time at the option of Borrower." On February 5, 1988,
concerned about the dwindling supply of low- and middle-income
rural housing in the face of increasing prepayments of mortgages by
§ 515 borrowers, Congress enacted the Emergency Low Income Housing
Preservation Act of 1987 (ELIHPA), which amended the Housing Act of
1949 to impose permanent restrictions upon prepayment of § 515
mortgages entered into before December 21, 1979. On May 30, 1997,
the
Franconia petitioners filed suit under the Tucker Act,
28 U. S. C. § 1491, charging that ELIHPA abridged the absolute
prepayment right set forth in their promissory notes and thereby
effected,
inter alia, a repudiation of their contracts. In
dismissing petitioners' contract claims as untimely under §
2501-which provides that a claim "shall be barred unless the
petition thereon is filed within six years after such claim first
accrues" -the Court of Federal Claims concluded that the claims
first accrued on the ELIHPA regulations' effective date. In
affirming on statute of limitations grounds, the Federal Circuit
ruled that, if the Government's continuing duty to allow
petitioners to prepay their loans was breached, the breach occurred
immediately upon ELIHPA's enactment date, over nine years before
petitioners filed their suit. The court rejected petitioners'
argument that ELIHPA's passage qualified as a repudiation, so that
their suit would be timely if filed within six years of either the
date performance fell due (the date they tendered prepayment) or
the date on which they elected to treat the repudiation as a
present breach. On September 16, 1998, the
Grass Valley
petitioners filed an action that was virtually identical to the
Franconia suit. The Court of Federal Claims dismissed for
the
*Together with
Grass Valley Terrace et al. v.
United
States (see this Court's Rule 12.4), also on certiorari to the
same court.
130
reasons it had dismissed the
Franconia claims, and the
Federal Circuit affirmed without opinion.
Held: Because ELIHPA's enactment qualified as a
repudiation of the parties' bargain, not a present breach of the
loan agreements, breach would occur, and the six-year limitations
period would commence to run, when a borrower tenders prepayment
and the Government then dishonors its obligation to accept the
tender and release its control over use of the property securing
the loan. Pp. 141-149.
(a) Resolution of two threshold matters narrows the scope of the
controversy. First, the requirement that the Government
unequivocally waive its sovereign immunity is satisfied here
because, once the United States waives immunity and does business
with its citizens, it does so much as a party never cloaked with
immunity. Cf.
Clearfield Trust Co. v.
United States,
318 U. S. 363,
369. Second, the Court, like the Government, accepts for purposes
of this decision that the loan contracts guaranteed the absolute
prepayment right petitioners allege. P. 141.
(b) Under applicable general contract law principles, whether
petitioners' claims were filed "within six years after [they] first
accrue[d]," § 2501, depends upon when the Government breached the
prepayment undertaking stated in the promissory notes. In declaring
ELIHPA a present breach of petitioners' loan contracts, the Federal
Circuit reasoned that the Government had but one obligation under
those agreements: to continue to allow borrowers the unfettered
right to prepay their loans at any time. If that continuing duty
was breached, the court maintained, the breach occurred
immediately, totally, and definitively, when ELIHPA took
away the borrowers' unfettered right to prepay. In so ruling, the
court incorrectly characterized the performance allegedly due from
the Government under the promissory notes. The Government's pledged
performance is properly comprehended as an obligation to accept
prepayment. Once the Government's obligation is thus correctly
characterized, the decisions below lose force. A promisor's failure
to perform at the time indicated for performance in the contract
establishes an immediate breach. But the promisor's renunciation of
a contractual duty
before the time fixed in the contract for
performance is a repudiation, which ripens into a breach prior to
the time for performance only if the promisee elects to treat it as
such, see
Roehm v.
Horst, 178 U. S. 1, 13. Viewed in
this light, ELIHPA effected a repudiation of the FmHA loan
contracts, not an immediate breach. ELIHPA conveyed the
Government's announcement that it would not perform as represented
in the promissory notes if and when, at some point in the future,
petitioners attempted to prepay their mortgages. Unless petitioners
treated ELIHPA as a present breach by filing suit prior to the
131
date indicated for performance, breach would occur when a
borrower attempted to prepay, for only then would the Government's
responsive performance become due. Pp. 141-144.
(c) The first of the Government's arguments to the contrary is
unpersuasive. The Government contends that § 2501's "first accrues"
qualification is meant to ensure that suits against the United
States are filed on the earliest possible date, thereby providing
the Government with reasonably prompt notice of the fiscal
implications of past enactments. However, § 2501's text is
unexceptional: A number of contemporaneous state statutes of
limitations applicable to suits between private parties also tie
the commencement of the limitations period to the date a claim
"first accrues." Equally telling, in its many years of applying and
interpreting § 2501, the Court of Federal Claims has never
attributed to the words "first accrues" the meaning the Government
now proposes. Instead, in other settings, that court has adopted
the repudiation doctrine in its traditional form when evaluating
the timeliness of suits governed by § 2501. Two practical
considerations reinforce the Court's conclusion. First, reading §
2501 as the Government proposes would seriously distort the
repudiation doctrine in Tucker Act suits because a party aggrieved
by the Government's renunciation of a contractual obligation
anticipating future performance would be compelled by the looming
limitations bar to forgo the usual option of awaiting the time
performance is due before filing suit for breach. Second, putting
prospective plaintiffs to the choice of either bringing suit soon
after the Government's repudiation or forever relinquishing their
claims would surely proliferate litigation, forcing the Government
to defend against highly speculative damages claims in a profusion
of suits, most of which would never have been brought under a less
novel interpretation of § 2501. Pp. 144-147.
(d) The Court also rejects the premise, and therefore the
conclusion, of the Government's second argument against application
of the repudiation doctrine. The Government contends that a
congressional enactment like ELIHPA that precludes the Government
from honoring a contractual obligation anticipating future
performance always constitutes a present breach because the agency
or official responsible for administering the contract is not free
to change its mind and render the requisite performance without
violating binding federal law. However, just as Congress may
announce the Government's intent to dishonor an obligation to
perform in the future through a duly enacted law, so may it retract
that renouncement prior to the time for performance, thereby
enabling the agency or contracting official to perform as promised.
Indeed, Congress changed its mind in just this manner before it
enacted ELIHPA. In 1979 amendments to the National Housing Act,
Congress
132
repudiated the promissory notes at issue here by conditioning
prepayment of all § 515 loans on the borrower's agreement to
maintain the low-income use of its property for a specified period.
One year later, Congress removed those conditions on pre-1979
loans, thereby retracting the repudiation. Hence, the fact that the
Government's repudiation here rested upon the enactment of a new
statute makes no significant difference.
Mobil Oil
Exploration &
Producing Southeast, Inc. v.
United
States, 530 U. S.
604, 619, 620. Pp. 147-148.
240 F.3d
1358; 7 Fed. Appx. 928, reversed and remanded.
GINSBURG, J., delivered the opinion for a unanimous Court.
Jeff H. Eckland argued the cause for petitioners. With
him on the briefs were
William L. Roberts and
Mark
J. Blando.
Matthew D. Roberts argued the cause for the United States. With
him on the brief were Acting Solicitor General Clement, Assistant
Attorney General McCallum, James A. Feldman, David M. Cohen, and
Mark L. Josephs.t
JUSTICE GINSBURG delivered the opinion of the Court. The two
cases consolidated for our review concern the timeliness of claims
filed against the United States under the Tucker Act, 28 U. S. C. §
1491. Petitioners are property owners who participated in a federal
program to promote development of affordable rental housing in
areas not traditionally served by conventional lenders. In exchange
for low-interest mortgage loans issued by the Farmers Home
Administration (FmHA), petitioners agreed to devote their
tBriefs of amici curiae urging reversal were filed for Bank of
America, FSB, et al. by Steven S. Rosenthal, Alan K. Palmer, Leo G.
Rydzewski, John C. Millian, Melvin C. Garbow, Howard N. Cayne,
David B. Bergman, Michael A. Johnson, Daniel
J. Goldberg,
William T. Reilly, and Stephen M. Forte; for the Council for
Affordable and Rural Housing by Carl A. S. Coan III; and for the
National Association of Home Builders by Thomas Jon Ward.
John C. Millian, Mark A. Perry, and Paul Blankenstein filed a
brief for John K. Castle et al. as amici curiae.
133
properties to low- and middle-income housing and to abide by
related restrictions during the life of the loans.
Petitioners allege that the promissory notes governing their
loans guaranteed the borrower the right to prepay at any time and
thereby gain release from the federal program and the restrictions
it places on the use of a participating owner's property. In the
suits that yielded the judgments before us, petitioners charged
that Congress abridged that release right in the Emergency Low
Income Housing Preservation Act of 1987 (ELIHPA or Act), 101 Stat.
1877, as amended, 42 U. S. C. § 1472(c) (1994 ed. and Supp. V).
That Act placed permanent restraints upon prepayment of FmHA loans.
Petitioners asserted in their complaints that ELIHPA effected both
a repudiation of their contracts and a taking of their property in
violation of the Fifth Amendment.
The Federal Circuit held petitioners' claims time barred under
28 U. S. C. § 2501, which prescribes that all Tucker Act claims
must be filed within six years of the date they "first accrue[d]."
In the Federal Circuit's view, passage of ELIHPA constituted an
immediate breach of the FmHA loan agreements and therefore
triggered the running of the limitations period. Petitioners filed
suit not "within six years of," but over nine years after, ELIHPA's
enactment. On that account, the Federal Circuit held their claims
untimely, and their suits properly dismissed.
Accepting for purposes of this decision that the loan contracts
guaranteed the absolute prepayment right petitioners allege, we
reverse the Federal Circuit's judgment. ELIHPA's enactment, we
conclude, qualified as a repudiation of the parties' bargain, not a
present breach of the loan agreements. Accordingly, breach would
occur, and the sixyear limitations period would commence to run,
when a borrower tenders prepayment and the Government then
dishonors its obligation to accept the tender and release its
control over use of the property that secured the loan.
134
I A
Under §§ 515 and 521 of the Housing Act of 1949, 76 Stat. 671,
82 Stat. 551, as amended, 42 U. S. C. §§ 1485, 1490a, the FmHA
makes direct loans to private, nonprofit entities to develop or
construct rural housing designed to serve the elderly and low- or
middle-income individuals and families.1 Section 515 loans require
the borrower,
inter alia, to execute various loan documents,
including a loan agreement, a promissory note, and a real estate
mortgage.
Before December 21, 1979, each petitioner entered into a loan
agreement with the FmHA under §§ 515 and 521 "to provide rental
housing and related facilities for eligible occupants ... in rural
areas." App. to Pet. for Cert. A165. In the loan agreements, each
petitioner certified that it was unable to obtain a comparable loan
in the commercial market. See
id., at Al77. The loan
agreements contained various provisions designed to ensure that the
projects were affordable for people with low incomes. Those
provisions included restrictions as to eligible tenants, the rents
petitioners could charge, and the rate of return petitioners could
realize, as well as requirements regarding the maintenance and
financial operations of each project. See
id., at A170-A174.
Each loan agreement also specified the length of the loan,
ordinarily 40 or 50 years.
The promissory notes executed by petitioners required payment of
the principal on each mortgage in scheduled installments, plus
interest. See
id., at A176-A177. The
1 Since 1994, the program has been entrusted to the Rural
Housing Service, known between 1994 and 1996 as Rural Housing and
Community Development Services. That agency was created by the
Secretary of Agriculture under authority provided by the Department
of Agriculture Reorganization Act of 1994, 108 Stat. 3219, as
amended, 110 Stat. 1128, 1131. See also 7 CFR § 2003.18 (2002)
(functional organization of Rural Housing Service). Our references
to the FmHA should be understood to include these successor
agencies.
135
notes also contained the prepayment provision curtailed by the
legislation involved in the litigation now before us. That
provision read: "Prepayments of scheduled installments, or any
portion thereof, may be made at any time at the option of
Borrower."
Id., at A176. No other provision of the loan
documents addressed prepayment.
In 1979, Congress found that many § 515 participants had prepaid
their mortgages, thus threatening the continued availability of
affordable rural housing. Concerned that "these projects [remain]
available to low and moderate income families for the entire
original term of the loan," H. R. Rep. No. 96-154, p. 43 (1979),
Congress amended the National Housing Act to stem the loss of
low-cost rural housing due to prepayments, see Housing and
Community Development Amendments of 1979, 93 Stat. 1101. In these
1979 amendments, Congress prohibited the FmHA from accepting
prepayment of any loan made before or after the date of enactment
unless the owner agreed to maintain the lowincome use of the rental
housing for a 15- year or 20- year period from the date of the
loan. 93 Stat. 1134-1135. That requirement could be avoided if the
FmHA determined that there was no longer a need for the low-cost
housing.
Id., at 1135.
The 1979 amendments applied to all program loans, past, present,
and future. In 1980, however, Congress further amended the National
Housing Act to eliminate retroactive application of the § 515
prepayment limitations imposed by the 1979 legislation. The Housing
and Community Development Act of 1980, 94 Stat. 1614, provided that
the prepayment restrictions would apply only to loans entered into
after December 21, 1979, the date that amendment was enacted. §
514, 94 Stat. 1671-1672. The 1980 Act also required the Secretary
of Agriculture to inform Congress of the repeal's adverse effects,
if any, on the availability of low-income housing.
Id., at
1672.
136
By 1987, Congress had again become concerned about the dwindling
supply of low- and moderate-income rural housing in the face of
increasing prepayments of mortgages under § 515.2 A House of
Representatives Committee found that owners were "prepay[ing] or
... refinanc[ing] their FmHA loans, without regard to the low
income and elderly tenants in these projects." H. R. Rep. No.
100-122, p. 53.
Responsive to that concern, Congress passed ELIHPA, which
amended the Housing Act of 1949 to impose permanent restrictions
upon prepayment of § 515 mortgages entered into before December 21,
1979. This legislation, enacted on February 5, 1988, provides that
before FmHA can accept an offer to prepay such a mortgage,
"the [FmHA] shall make reasonable efforts to enter into an
agreement with the borrower under which the borrower will make a
binding commitment to extend the low income use of the assisted
housing and related facilities involved for not less than the
20-year period beginning on the date on which the agreement is
executed." 42 U. s. C. § 1472(c)(4)(A) (1994 ed.).
The legislation further provides that the FmHA may include
incentives in such an agreement, including an increase in the rate
of return on investment, reduction of the interest rate on the
loan, and an additional loan to the borrower. § 1472(c)(4)(B) (1994
ed. and Supp. V).
Under ELIHPA, if the FmHA determines after a "reasonable period"
that an agreement cannot be reached, the owner who sought to prepay
must offer to sell the housing to "any qualified nonprofit
organization or public agency at a fair market value determined by
2 independent appraisers." § 1472(c)(5)(A)(i) (1994 ed.). If an
offer to buy is not
2 In 1986, Congress had passed a temporary moratorium that
precluded § 515 prepayments in most cases. The moratorium
originally was to expire in 1987, but it was extended into 1988 by
another temporary measure. See note following 42 U. S. C. § 1472,
p. 163 (1994 ed.).
137
made by a nonprofit organization or agency within 180 days, the
FmHA may accept the owner's offer to prepay. § 1472(c)(5)(A)(ii).
The offer-for-sale requirement may be avoided if the FmHA
determines that prepayment will not "materially affec[t]" housing
opportunities for minorities and one of two other conditions is
met: Prepayment will not displace the tenants of the affected
housing, or there is "an adequate supply of safe, decent, and
affordable rental housing within the market area" and "sufficient
actions have been taken to ensure" that such housing "will be made
available" to displaced tenants. § 1472(c)(5)(G)(ii).
ELIHPA's implementing regulations establish a process by which
the FmHA addresses prepayment requests. Under those procedures, the
FmHA first "develo[ps] an incentive offer," making a "reasonable
effort ... to enter into an agreement with the borrower to maintain
the housing for low-income use that takes into consideration the
economic loss the borrower may suffer by foregoing
[sic]
prepayment." 7 CFR § 1965.210 (2002). Only if the borrower rejects
that offer will the FmHA attempt to make the
determinations-regarding the effect on minority housing
opportunities, the displacement of tenants, and the supply of
affordable housing in the market-required by 42 U. S. C. §
1472(c)(5)(G) before prepayment can be accepted. 7 CFR §
1965.215(a) (2002).3
B
Petitioners in
Franconia filed this action in the United
States Court of Federal Claims on May 30, 1997. Plaintiffs included
petitioners-all of whom had entered into loan agreements before
December 21, 1979, and were therefore
3 In 1992, Congress passed the Housing and Community Development
Act of 1992, 106 Stat. 3672, codified in relevant part at 42 U. S.
C. § 1472(c) (1992 legislation). That provision, which had no
effect on petitioners' loans, extended ELIHPA's restrictions to
loans made after those of petitioners, i.
e., loans made
from December 21, 1979, through 1989. See 106 Stat. 3841.
138
subject to ELIHPA-and others, who had entered into loan
agreements after December 21, 1979, and were therefore unaffected
by the Act. See App. to Pet. for Cert. A3, n. 2.4 Petitioners
alleged that ELIHPA repudiated their loan contracts, which, they
asserted, gave them the right "to terminate their participation in
the Government's housing program by exercising their option to
prepay at any time."
Id., at A112. Their complaint sought
relief on two theories: breach of contract and a violation of the
Fifth Amendment's proscription against taking property without just
compensation. See
id., at A132-A133.
The Court of Federal Claims granted the Government's motion to
dismiss petitioners' contract claims as barred by the six-year
statute of limitations in 28 U. S. C. § 2501. 43 Fed. Cl. 702
(1999). That provision states: "Every claim of which the United
States Court of Federal Claims has jurisdiction shall be barred
unless the petition thereon is filed within six years after such
claim first accrues." The court concluded that petitioners'
contract claims first accrued on May 23, 1988, the effective date
of regulations implementing ELIHPA.
Id., at 709. That was
so, the court said, because those regulations breached the only
performance required of the Government under the promissory notes:
"to keep its promise to allow borrowers an unfettered prepayment
right."
Id., at 710. The court also dismissed petitioners'
takings claims
sua sponte; because "the [Government] conduct
... alleged to have constituted a taking" was "Congress's change of
the prepayment option," the court reasoned, any claim based on that
conduct "accrued at the time of the 1988 legislation."
Id.,
at 711.
The Federal Circuit affirmed the dismissal of petitioners'
claims on timeliness grounds.
240 F.3d
1358 (2001). The
4 The claims of the latter group of
Franconia plaintiffs
remain pending before the Court of Federal Claims. See App. to Pet.
for Cert. A3, n.2.
139
Court of Appeals agreed with the Court of Federal Claims on the
respective benefits and burdens generated by the promissory notes:
Petitioners enjoyed "an unfettered right to prepay their loans at
any time,"
id., at 1363, while the Government had an
obligation "to continue to allow borrowers" that option,
ibid. If the Government's "continuing duty was breached,"
the court concluded, "the breach occurred immediately upon
enactment of ELIHPA because, by its terms, ELIHPA took away the
borrowers' unfettered right of prepayment."
Ibid. Thus, the
court ruled, the statute of limitations began to run on February 5,
1988, the date of ELIHPA's passage, see
id., at 1364; 5
given that limitationstriggering date, the court held, petitioners'
claims, filed over nine years post-ELIHPA, were time barred.
In holding petitioners' claims untimely, the Federal Circuit
rejected the argument pressed by petitioners that the passage of
ELIHPA qualified as a repudiation. Were ELIHPA so regarded,
petitioners' suit would be timely if filed within six years of
either the date performance fell due (the date petitioners tendered
prepayment) or the date on which petitioners elected to treat the
repudiation as a present breach. "An anticipatory repudiation
occurs," the Court of Appeals recognized, "when an obligor
communicates to an obligee that he will commit a breach in the
future."
Id., at 1363 (internal quotation marks omitted).
"The doctrine of anticipatory repudiation does not apply in this
case," the court reasoned, because after ELIHPA revoked the promise
to allow unrestricted prepayment, the Government owed no future
performance under the contracts.
Id., at 1364.
5 The Federal Circuit thus disagreed with the Court of Federal
Claims in one respect: The former concluded that petitioners'
claims had accrued on the date of ELIHPA's enactment, while the
latter held that those claims had accrued on the effective date of
regulations implementing the Act. 240 F. 3d, at 1365, n. 3. This
disagreement is irrelevant to, and rendered academic by, our
resolution of the petitions.
140
Petitioners' takings claims were time barred for essentially the
same reason, the Federal Circuit held. The "property" allegedly
taken without just compensation was petitioners' contractual "right
to prepay their FmHA loans at any time,"
id., at 1365; the
takings claim thus arose when, upon passage of ELIHPA, the
Government "took away and conclusively abolished" the unrestricted
prepayment option,
id., at 1366.6
On September 16, 1998, the
Grass Valley petitioners, all
of whom had entered into § 515 loan agreements before December 21,
1979, joined by other plaintiffs with post-1979 loans, filed an
action in the Court of Federal Claims virtually identical to the
Franconia action. On April 12, 2000, that court granted the
Government's motion to dismiss the
Grass Valley petitioners'
contract claims for the reasons it had dismissed the claims of the
Franconia petitioners. 46 Fed. Cl. 629, 633-635 (2000). The
Federal Circuit affirmed without opinion. Judgt. order reported at
7 Fed. Appx. 928 (2001).7
We granted certiorari, 534 U. S. 1073 (2002), and now reverse
the two judgments of the Federal Circuit before us for review.
6 Like the Court of Federal Claims, see 43 Fed. Cl. 702, 708-709
(1999), the Federal Circuit rejected petitioners' "alternative
argument" that even if the limitations period commenced to run upon
enactment of legislation installing prepayment restrictions, the
1992 legislation, rather than ELIHPA, served as the operative
provision. 240 F. 3d, at 1365, and n. 4. Petitioners contended that
ELIHPA represented an emergency measure that curtailed prepayment
rights only temporarily; the definitive legislative action, they
maintained, occurred later, when the 1992 legislation made
curtailment of their prepayment rights permanent.
Id., at
1365. The Federal Circuit concluded that although Congress had
designated certain provisions in ELIHPA "interim measures,"
ibid. (internal quotation marks omitted), "no similar
language ... indicate[s] that [ELIHPA's] restrictions on FmHA loan
prepayments were anything but permanent as to" borrowers in
petitioners' situation,
ibid.
7 The Court of Federal Claims dismissed the
Grass Valley
petitioners' takings claims as untimely in a separate decision. 51
Fed. Cl. 436, 439 (2002).
141
II A
A waiver of the sovereign immunity of the United States "cannot
be implied but must be unequivocally expressed."
United
States v.
King, 395 U. S. 1, 4 (1969). That
requirement is satisfied here. Once the United States waives its
immunity and does business with its citizens, it does so much as a
party never cloaked with immunity. Cf.
Clearfield Trust Co.
v.
United States, 318 U. S. 363, 369 (1943)
("The United States does business on business terms." (internal
quotation marks omitted)).
Another threshold matter confines this controversy. For purposes
of our disposition, the United States agrees, it may be assumed
that petitioners obtained precisely the promise they allege-a
promise that permits them an unfettered right to prepay their
mortgages any time over the life of the loans, thereby gaining
release from federal restrictions on the use of their property. See
Brief for United States 18-19; Tr. of Oral Arg. 29-30. The sole
issue before us is thus cleanly presented: were petitioners'
complaints initiated within the six-year limitations period
prescribed in 28 U. S. C. § 2501?
"When the United States enters into contract relations, its
rights and duties therein are governed generally by the law
applicable to contracts between private individuals."
Mobil Oil
Exploration &
Producing Southeast, Inc. v.
United
States, 530 U. S.
604, 607 (2000) (internal quotation marks omitted). Under
applicable "principles of general contract law,"
Priebe
&
Sons, Inc. v.
United States, 332 U. S. 407, 411
(1947), whether petitioners' claims were filed "within six years
after [they] first accrue[d]," 28 U. S. C. § 2501, depends upon
when the Government breached the prepayment undertaking stated in
the promissory notes. See 1 C. Corman, Limitations of Actions §
7.2.1, p. 482 (1991) ("The cause of action for breach of contract
accrues, and the statute of limitations begins to run, at the time
of the breach." (footnote
142
omitted)); see also 18 W. Jaeger, Williston on Contracts §
2021A, p. 697 (3d ed. 1978) (same).
In declaring ELIHPA a present breach of petitioners' loan
contracts, the Federal Circuit reasoned that the Government had but
one obligation under those agreements: "to continue to allow
borrowers the unfettered right to prepay their loans at any time."
240 F. 3d, at 1363; see also 43 Fed. Cl., at 710 (Government's
contractual duty was "to keep its promise to allow borrowers an
unfettered prepayment right"). If that continuing duty was
breached, the court maintained, the breach occurred
immediately, totally, and definitively when ELIHPA took away
the borrowers' unfettered right to prepay. See 240 F. 3d, at 1363.
The Court of Appeals so ruled despite petitioners' insistence that
"the government's performance obligation under the contracts was to
accept prepayment" whenever tendered during the long life of
the loans, even decades into the future.
Id., at 1362
(emphasis added); see also 43 Fed. Cl., at 710.
The Federal Circuit, we are persuaded, incorrectly characterized
the performance allegedly due from the Government under the
promissory notes. If petitioners enjoyed a "right to prepay their
loans at any time," 240 F. 3d, at 1363, then necessarily the
Government had a corresponding obligation to accept prepayment and
execute the appropriate releases. See Brief for Petitioners 5-6.
Absent an obligation on the lender to accept prepayment, the
obligation "to allow" borrowers to prepay would be meaningless. A
loan contract of such incomplete design would be illusory. See J.
Murray, Contracts § 2, p. 5 (2d rev. ed. 1974) (promise required to
create a binding contract must be an "undertaking or commitment to
do or refrain from doing [some]thing in the future").
Once the Government's pledged performance is properly
comprehended as an obligation to accept prepayment, the error in
the Federal Circuit's reasoning becomes apparent. Failure by the
promisor to perform at the time indicated for performance in the
contract establishes an immediate
143
breach. See Restatement (Second) of Contracts § 235(2) (1979)
(hereinafter Restatement) ("When performance of a duty under a
contract is due[,] any non-performance is a breach."); Murray,
supra, § 206, at 417. But the promisor's renunciation of a
"contractual duty
before the time fixed in the contract for
... performance" is a repudiation. 4 A. Corbin, Contracts § 959, p.
855 (1951) (emphasis added); Restatement § 250 (repudiation entails
a statement or "voluntary affirmative act" indicating that the
promisor "will commit a breach" when performance becomes due). Such
a repudiation ripens into a breach prior to the time for
performance only if the promisee "elects to treat it as such." See
Roehm v.
Horst, 178 U. S. 1, 13 (1900)
(repudiation "give[s] the promisee the right of electing either to
... wait till the time for [the promisor's] performance has
arrived, or to act upon [the renunciation] and treat it as a final
assertion by the promisor that he is no longer bound by the
contract").
Viewed in this light, ELIHPA effected a repudiation of the FmHA
loan contracts, not an immediate breach. The Act conveyed an
announcement by the Government that it would not perform as
represented in the promissory notes if and when, at some point in
the future, petitioners attempted to prepay their mortgages. See
Restatement § 250, Comment
b ("[A] statement of intention
not to perform except on conditions which go beyond the contract
constitutes a repudiation." (internal quotation marks omitted));
Murray,
supra, § 208, at 421. Unless petitioners treated
ELIHPA as a present breach by filing suit prior to the date
indicated for performance, breach would occur when a borrower
attempted to prepay, for only at that time would the Government's
responsive performance become due.8
8 The record indicates that at least one petitioner has
attempted to prepay, see App. to Pet. for Cert. A157-A158, but
contains no information about how many others have done so or when
any such attempts took place, see 43 Fed. Cl., at 707. Application
of our holding to each petitioner in light of such determinations
is a task for the lower courts on remand.
144
In sum, once it is understood that ELIHPA is most sensibly
characterized as a repudiation, the decisions below lose force. To
recapitulate, "[t]he time of accrual ... depends on whether the
injured party chooses to treat the ... repudiation as a present
breach." 1 C. Corman, Limitation of Actions § 7.2.1, p. 488 (1991).
If that party "[e]lects to place the repudiator in breach before
the performance date, the accrual date of the cause of action is
accelerated from [the] time of performance to the date of such
election."
Id., at 488-489. But if the injured party instead
opts to await performance, "the cause of action accrues, and the
statute of limitations commences to run, from the time fixed for
performance rather than from the earlier date of repudiation."
Id., at 488.
The Government draws no distinction "between a duty to allow
petitioners to prepay and a duty to accept tendered prepayments";
"any such distinction," the Government acknowledges, "would be
without significance." Brief for United States 33. Indeed, the
Government recognizes, if petitioners had an "unfettered right to
prepay," then, "of course," that right would be complemented by an
"obligation to accept any prepayment tendered."
Ibid. In
defense of the judgment below, the Government relies on two other
grounds.
First, the Government draws upon the text of § 2501, which bars
any claims not "filed within six years after [the] claim first
accrues." The words "first accrues," the Government contends, are
key. See
id., at 11. Those words, according to the
Government, convey Congress' intent to guard the sovereign against
claims that might be deemed timely under statutes of limitations
applicable to private parties.
Id., at 28. As the Government
reads § 2501, the "first accrues" qualification ensures that suits
against the United States are filed on "the earliest possible
date,"
id., at 17, thereby providing the Government with
"reasonably prompt notice of the fiscal implications of past
enactments,"
id.,
145
at 16. See
ibid. ("[S]trict construction of [§ 2501] ...
serves the salutary purpose of ensuring that a Congress close to
the one that enacted the statute [alleged to have caused a breach
of contract]-rather than a Congress serving perhaps many decades
later-may and must address the consequences."); see Tr. of Oral
Arg. 45-46.
We do not agree that § 2501 creates a special accrual rule for
suits against the United States. Contrary to the Government's
contention, the text of § 2501 is unexceptional: A number of
contemporaneous state statutes of limitations applicable to suits
between private parties also tie the commencement of the
limitations period to the date a claim "first accrues." See J.
Angell, Limitations of Actions 536-588 (6th ed. 1876) (quoting
state statutes of limitations). Equally telling, in its many years
of applying and interpreting § 2501, the Court of Federal Claims
has never attributed to the words "first accrues" the meaning the
Government now proposes. Instead, in other settings, that court has
adopted the repudiation doctrine in its traditional form when
evaluating the timeliness of suits governed by § 2501. See
Plaintiffs in Winstar-Related Cases v.
United States,
37 Fed. Cl. 174, 183-184 (1997), aff'd
sub nom. Ariadne
Financial Services Pty. Ltd. v.
United States, 133 F.3d
874 (CA Fed. 1998). In line with our recognition that
limitations principles should generally apply to the Government "in
the same way that" they apply to private parties,
Irwin v.
Department of Veterans Affairs, 498 U. S. 89, 95 (1990),
we reject the Government's proposed construction of § 2501. That
position, we conclude, presents an "unduly restrictiv[e]" reading
of the congressional waiver of sovereign immunity,
Bowen v.
City of New York, 476 U. S. 467, 479
(1986), rather than "a realistic assessment of legislative intent,"
Irwin, 498 U. S., at 95.9
9 As petitioners observe, see Reply Brief 6, n. 6, the "first
accrues" qualification might serve a meaningful purpose in the
context of tolling of disabilities for successive claimants. In
that context, the qualification would ensure that suit could be
delayed only during the disability of the claim-
146
Two practical considerations reinforce this conclusion.
Cf.
Crown Coat Front Co. v.
United States,
386 U. S. 503,
517 (1967) (the words "first accrues" must be interpreted "with due
regard to those practical ends which are to be served by any
limitation of the time within which an action must be brought"
(internal quotation marks omitted)). Reading § 2501 as the
Government proposes would seriously distort the repudiation
doctrine in suits brought under the Tucker Act. Assuming a claim
could "first accrue" for limitations purposes on the date of
repudiation, but see
supra, at 144, a party aggrieved by the
Government's renunciation of a contractual obligation anticipating
future performance would be compelled by the looming limitations
bar to forgo the usual option of awaiting the time performance is
due before filing an action for breach. The Government's
construction of § 2501 would thus convert the repudiation doctrine
from a shield for the promisee into a sword by which the Government
could invoke its own wrongdoing to defeat otherwise timely suits.
As Professor Corbin explained, "[t]he plaintiff should not be
penalized for leaving to the defendant an opportunity to retract
his wrongful repudiation; and he would be so penalized if the
statutory period of limitation is held to begin to run against him
immediately." Corbin, Contracts § 989, at 967; see
Roehm v.
Horst, 178 U. S., at 10 ("[I]t seems reasonable to allow an
option to the injured party, either to sue immediately, or to wait
till the time when the act was to be done, ... which may be
advantageous to the innocent party.").
There is also reason to doubt that the Government's reading of §
2501 would inure to the benefit of the United States. Putting
prospective plaintiffs to the choice of either bringing suit soon
after the Government's repudiation or forever relinquishing their
claims would surely proliferate litigation.
ant to whom a right of action first accrued; successive
claimants laboring under a disability would be unprotected by any
tolling proviso. See J. Angell, Limitations of Actions 488, and n.
2 (6th ed. 1876).
147
Every borrower of FmHA loans, for example, would be forced to
sue the Government within six years of ELIHPA's enactment in order
to preserve a claim stemming from that Act. Faced with the prospect
of forever forgoing such a claim, even a borrower that had not
previously wished to prepay might well conclude that early exit
from the FmHA program is the only safe course. The Government would
thus find itself defending against highly speculative damages
claims in a profusion of lawsuits, most of which would never have
been brought under a less novel interpretation of § 2501. See Tr.
of Oral Arg. 33-34.10
The Government also seeks to avoid the repudiation doctrine by
attacking as "futile" petitioners' "search for an exact parallel in
contracts solely between private parties." Brief for United States
13. The law of repudiation does not govern here, the Government
ultimately contends, because the "statement of intent not to
perform" on which petitioners base their claim is an Act of
Congress.
Id., at 24. According to the Government, a
congressional enactment like ELIHPA that precludes the Government
from honoring a contractual obligation anticipating future
performance always constitutes a present breach. This is so, the
Government maintains, because "the promisor"-the agency or official
responsible for administering the contract-does not
10 The Government's reliance on
McMahon v.
United
States, 342 U. S.
25 (1951), is misplaced. Brief for United States 29-30. The
Court there rejected an interpretation of the Suits in Admiralty
Act that would have given tort plaintiffs "an option as to when
they will choose to start the period of limitation of an action
against the United States." 342 U. S., at 27. The reasoning in that
case does not apply to petitioners' claims, which arise out of
contracts in which the Government allegedly granted borrowers an
option to demand performance, and thereby precipitate breach, at
any time. See
supra, at 141. And unlike the position
rejected in
McMahon, our ruling today ensures that suit must
be brought within a fixed period after the date of injury-in this
case, no later than six years after the Government's refusal to
accept prepayment in accord with the terms of the promissory
notes.
148
"remai[n] free to change its mind and render the requisite
performance" without violating binding federal law.
Id., at
27. Accordingly, the Government concludes, the essential purpose of
the repudiation doctrine-to avoid an unnecessary lawsuit by
allowing the promisor an opportunity to adhere to its
undertaking-is inapplicable.
We reject the Government's premise, and therefore its
conclusion. Just as Congress may announce the Government's intent
to dishonor an obligation to perform in the future through a duly
enacted law, so may it retract that renouncement prior to the time
for performance, thereby enabling the agency or contracting
official to perform as promised. Indeed, Congress "change[d] its
mind" in just this manner before it enacted ELIHPA.
Ibid. In
the 1979 amendments to the National Housing Act, Congress
repudiated the promissory notes at issue here by conditioning
prepayment of all § 515 loans on the borrower's agreement to
maintain the low-income use of its property for a specified period.
See Housing and Community Development Amendments of 1979, 93 Stat.
1134-1135. One year later, Congress removed those conditions on
pre-1979 loans, thereby retracting the repudiation. See Housing and
Community Development Act of 1980, 94 Stat. 1671-1672;
supra, at 135.
We comprehend no reason why an Act of Congress may not
constitute a repudiation of a contract to which the United States
is a party. Congress may renounce the Government's contractual
duties without triggering an immediate breach because Congress may
withdraw that repudiation if given the opportunity to do so.
"Hence, ... the fact that [the Government's] repudiation rested
upon the enactment of a new statute makes no significant
difference."
Mobil Oil, 530 U. S., at 620; see
id.,
at 619 ("[I]f legislation passed by Congress and signed by the
President is not a 'statement by the obligor'" capable of
triggering a repudiation, "it is difficult to imagine what would
constitute such a statement." (quoting Restatement § 250)).
149
B
To answer the question presented-when does the statute of
limitations on petitioners' claims begin to run, see Pet. for Cert.
i-we need not separately address petitioners' alternative theory of
recovery based on the Takings Clause of the Fifth Amendment. The
Federal Circuit's holding that takings relief was time barred
hinged entirely on its conclusion that petitioners' contract claims
accrued upon passage of ELIHPA. See 240 F. 3d, at 1365-1366.
Because that conclusion was incorrect, we hold, the Federal Circuit
erred in dismissing petitioners' takings theory on grounds of
untimeliness.
***
Concluding that each petitioner's claim is timely if filed
within six years of a wrongly rejected tender of prepayment, we
reverse the judgments of the Federal Circuit and remand the
Franconia and
Grass Valley cases reviewed herein for
further proceedings consistent with this opinion.
It is so ordered.