SUPREME COURT OF THE UNITED STATES
_________________
No. 23–975
_________________
SEVEN COUNTY INFRASTRUCTURE COALITION,
et al., PETITIONERS
v. EAGLE COUNTY, COLORADO,
et al.
on writ of certiorari to the united states
court of appeals for the district of columbia circuit
[May 29, 2025]
Justice Kavanaugh delivered the opinion of the
Court.
Some 55 years ago, Congress passed and President
Nixon signed the National Environmental Policy Act, known as NEPA.
For certain infrastructure projects that are built, funded, or
approved by the Federal Government, NEPA requires federal agencies
to prepare an environmental impact statement, or EIS. The EIS must
address the significant environmental effects of a proposed project
and identify feasible alternatives that could mitigate those
effects.
NEPA was the first of several landmark
environmental laws enacted by Congress in the 1970s. Subsequent
statutes included the Clean Air Amendments of 1970, the Clean Water
Act of 1972, and the Endangered Species Act of 1973, among
others.
Unlike those later-enacted laws, however, NEPA
imposes no substantive environmental obligations or restrictions.
NEPA is a purely procedural statute that, as relevant here, simply
requires an agency to prepare an EIS—in essence, a report.
Importantly, NEPA does not require the agency to weigh
environmental consequences in any particular way. Rather, an agency
may weigh environmental consequences as the agency reasonably sees
fit under its governing statute and any relevant substantive
environmental laws.
Simply stated, NEPA is a procedural cross-check,
not a substantive roadblock. The goal of the law is to inform
agency decisionmaking, not to paralyze it.
In this case, the U. S. Surface Transportation
Board considered a proposal by a group of seven Utah counties for
the construction and operation of an approximately 88-mile railroad
line in northeastern Utah. Under federal law, the Board determines
whether to approve construction of new railroad lines. The railroad
line here would connect Utah’s oil-rich Uinta Basin—a rural
territory roughly the size of the State of Maryland—to the national
rail network. By doing so, the new railroad line would facilitate
the transportation of crude oil from Utah to refineries in
Louisiana, Texas, and elsewhere. And the project would bring
significant economic development and jobs to the isolated Uinta
Basin by better connecting the Basin to the national economy.
For that proposed 88-mile Utah railroad line,
the Board prepared an extraordinarily lengthy EIS, spanning more
than 3,600 pages of environmental analysis. The Board’s EIS
addressed the environmental effects of the railroad line. But the
U. S. Court of Appeals for the D. C. Circuit nonetheless
faulted the EIS for not sufficiently considering the environmental
effects of projects separate from the railroad line
itself—primarily, the environmental effects that could ensue from
(i) increased oil drilling upstream in the Uinta Basin and (ii)
increased oil refining downstream along the Gulf Coast of Louisiana
and Texas.
On that basis, the D. C. Circuit vacated
the Board’s EIS and the Board’s approval of the 88-mile railroad
line. As a result, construction still has not begun even though the
Board approved the project back in December 2021.
We reverse. First, the D. C. Circuit did
not afford the Board the substantial judicial deference required in
NEPA cases. Second, the D. C. Circuit ordered the Board to
address the environmental effects of projects separate in time or
place from the construction and operation of the railroad line. But
NEPA requires agencies to focus on the environmental effects of the
project at issue. Under NEPA, the Board’s EIS did not need to
address the environmental effects of upstream oil drilling or
downstream oil refining. Rather, it needed to address only the
effects of the 88-mile railroad line. And the Board’s EIS did
so.
I
Under federal law, new railroad construction
and operation must first be approved by the U. S. Surface
Transportation Board. 49 U. S. C. §10901. After receiving
an application for a new railroad line, the Board issues a public
notice and initiates an agency proceeding to review the proposal;
alternatively, the Board may streamline approval through a
statutory exemption process. §§10101, 10502, 10901. In addition,
for covered projects, NEPA compels the Board to prepare an
environmental impact statement, or EIS.
In 2020, the Seven County Infrastructure
Coalition—a group of seven Utah counties—applied to the Board for
approval of an 88-mile railroad line in northeastern Utah. The new
railroad line would connect the Uinta Basin with the interstate
freight rail network—and via that network, to refineries in
Louisiana, Texas, and other destinations.
The Uinta Basin contains significant quantities
of crude oil and other fossil fuels. The Uinta Basin Railway would
provide oil producers a more efficient option for transporting oil
out of the Basin to refineries. As of now, oil from the Basin is
carried by trucks that must navigate mountain passes on narrow
roads, a difficult and slow journey in any season.
The Board’s environmental review of the Uinta
Basin Railway followed standard NEPA procedures. In October 2020,
the Board issued a draft EIS and invited public comment. During the
public comment period, the Board held six public meetings and
collected more than 1,900 comments. In August 2021, the Board
published its final EIS.
All told, the Board’s final EIS clocked in at
more than 3,600 pages. The EIS identified and analyzed numerous
“significant and adverse impacts that could occur as a result” of
the railroad line’s construction and operation—including
disruptions to local wetlands, land use, and recreation. App. 121;
see
id., at 94–105, 121–126, 206–347. The EIS likewise
addressed several “minor impacts,” such as air pollution and
big-game movement around the construction site.
Id., at 126;
see
id., at 126–134, 251–259, 309–325.
The EIS also noted, but did not fully analyze,
the potential effects of increased upstream oil drilling in the
Uinta Basin and increased downstream refining of crude oil carried
by the railroad.
Id., at 135, 348–482, 511–516, 520–534,
539–543.
As to the environmental effects of upstream oil
drilling, the EIS explained why further analysis of those
“potential future, as yet unplanned, oil and gas development
projects” was not needed.
Id., at 520. To begin with, the
project at issue was an 88-mile railroad line, not an oil well or a
drilling permit in the Uinta Basin. Moreover, the Board possesses
“no authority or control over potential future oil and gas
development” in the Basin.
Id., at 522. Future projects
would be “subject to the approval processes of other federal,
state, local, and tribal agencies.”
Ibid. In any event, the
environmental effects of future oil and gas development in the
Basin are “speculative” and attenuated from the project at hand.
Id., at 525; see
id., at 525–527 (citing
Department of Transportation v.
Public Citizen,
541 U.S.
752, 767–768, 770 (2004)).
As for the environmental effects of downstream
oil refining projects, the Board recognized that “trains
originating on the proposed rail line would transport crude oil to
markets in other regions of the United States,” such as Louisiana
and Texas, and that oil refining (and the associated effects on the
environment) could increase in those locations as a result. App.
477; see
id., at 477–482. But the identity of specific
destinations “would depend on the ability and willingness of
refineries in other markets to receive rail cars carrying Uinta
Basin crude oil and process the oil in their refineries.”
Id., at 477. Moreover, the Board “would have no role in
approving or regulating the production, refining, or use” of Uinta
Basin crude oil.
Id., at 540–541. So the Board did not fully
evaluate the effects of additional oil refining along the Gulf
Coast.
In December 2021, a few months after issuing the
final EIS, the Board approved the construction and operation of the
Uinta Basin Railway. Recognizing that “rail construction projects
are in the public interest,” the Board concluded that the new
railroad line would “have substantial transportation and economic
benefits,” and that those benefits outweighed the environmental
impacts identified in the EIS. App. to Pet. for Cert. 121a, 119a;
see
id., at 118a–121a.
In the wake of the Board’s final approval, a
Colorado county and several environmental organizations sued by
filing petitions for review in the U. S. Court of Appeals for the
D. C. Circuit.
The D. C. Circuit found “numerous NEPA
violations arising from the EIS.”
Eagle Cty. v.
Surface
Transp. Bd., 82 F. 4th 1152, 1196 (2023). In the court’s
view, the Board “failed” to take “the requisite ‘hard look’ at all
of the environmental impacts of the Railway.”
Id., at
1175.
Specifically, the Court of Appeals held that the
Board impermissibly limited its analysis of upstream and downstream
projects. The court concluded that the environmental effects from
oil drilling in the Uinta Basin and oil refining along the Gulf
Coast were “ ‘reasonably foreseeable impacts’ ” that the
EIS should have analyzed more extensively.
Id., at 1177. The
court rejected the Board’s argument that those effects would arise
from other projects (upstream oil drilling, downstream oil
refining, and the like) that are separate from the current project
and regulated by other agencies.
Id., at 1177–1180 (citing
Sierra Club v.
FERC, 867 F.3d 1357, 1372–1375 (CADC
2017) (
Sabal Trail)).
Based on the deficiencies it found in the EIS,
the Court of Appeals vacated the EIS and the Board’s final approval
order. 82 F. 4th, at 1196. The Coalition and the Uinta Basin
Railway sought review in this Court, and we granted certiorari. 602
U. S. ___ (2024).
II
For certain infrastructure projects that are
built, funded, or approved by the Federal Government, NEPA requires
federal agencies to prepare an environmental impact statement, or
EIS, identifying significant environmental effects of the projects,
as well as feasible alternatives. The law ensures that the agency
and the public are aware of the environmental consequences of
proposed projects. Properly applied, NEPA helps agencies to make
better decisions and to ensure good project management.
Importantly, however, NEPA is purely procedural.
In ultimately deciding whether to build, fund, or approve a
project, an “agency is not constrained by NEPA from deciding that
other values outweigh the environmental costs.”
Robertson v.
Methow Valley Citizens Council,
490
U.S. 332, 350 (1989). Otherwise stated, NEPA “does not mandate
particular results, but simply prescribes the necessary process”
for an agency’s environmental review of a project.
Ibid.;
see
Department of Transportation v.
Public Citizen,
541 U.S.
752, 756–757 (2004);
Marsh v.
Oregon Natural
Resources Council,
490 U.S.
360, 370–372 (1989);
Baltimore Gas & Elec. Co. v.
Natural Resources Defense Council, Inc.,
462 U.S.
87, 97–98 (1983);
Strycker’s Bay Neighborhood Council,
Inc. v.
Karlen,
444 U.S.
223, 227–228 (1980);
Vermont Yankee Nuclear Power Corp.
v.
Natural Resources Defense Council, Inc.,
435 U.S.
519, 558 (1978);
Kleppe v.
Sierra Club,
427 U.S.
390, 410, n. 21 (1976).[
1]
Here, the Board’s EIS evaluated the
environmental effects of the proposed 88-mile railroad line in
Utah’s rural Uinta Basin. But the D. C. Circuit, following
Circuit precedent applying NEPA, concluded that the EIS did not
sufficiently address the reasonably foreseeable environmental
impacts of increased upstream oil drilling in the Uinta Basin, as
well as the environmental effects of increased downstream oil
refining along the Gulf Coast. 82 F. 4th, at 1196.
As we will explain, we disagree with the
D. C. Circuit’s decision on two grounds. First, the court did
not afford the Board the substantial judicial deference required in
NEPA cases. Second, the court incorrectly interpreted NEPA to
require the Board to consider the environmental effects of upstream
and downstream projects that are separate in time or place from the
Uinta Basin Railway.
A
Since the early 1970s, federal courts have
reviewed NEPA cases. Over time, some courts have assumed an
aggressive role in policing agency compliance with NEPA. Other
courts have adopted a more restrained approach. In light of the
continuing confusion and disagreement in the Courts of Appeals over
how to handle NEPA cases, we think it important to reiterate and
clarify the fundamental principles of judicial review applicable in
those cases. As we will explain, the central principle of judicial
review in NEPA cases is deference.[
2]
As a general matter, when an agency interprets a
statute, judicial review of the agency’s interpretation is
de novo. See
Loper Bright Enterprises v.
Raimondo, 603 U.S. 369, 391–392 (2024). But when an agency
exercises discretion granted by a statute, judicial review is
typically conducted under the Administrative Procedure Act’s
deferential arbitrary-and-capricious standard. Under that standard,
a court asks not whether it agrees with the agency decision, but
rather only whether the agency action was reasonable and reasonably
explained. See
Motor Vehicle Mfrs. Assn. of United States,
Inc. v.
State Farm Mut. Automobile Ins. Co.,
463 U.S.
29, 43 (1983);
FCC v.
Prometheus Radio Project,
592 U.S. 414, 423 (2021).
When a party argues that an agency action was
arbitrary and capricious due to a deficiency in an EIS, the
reviewing court must account for the fact that NEPA is a
purely
procedural statute. Under NEPA, an agency’s only obligation is
to prepare an adequate report. “NEPA requires no more.”
Strycker’s Bay Neighborhood Council, 444 U. S., at 228.
Unlike a plethora of other federal environmental statutes (such as
the Clean Air Act, the Clean Water Act, etc.), NEPA imposes no
substantive constraints on the agency’s ultimate decision to
build, fund, or approve a proposed project. So when reviewing an
agency’s EIS, “the only role for a court” is to confirm that the
agency has addressed environmental consequences and feasible
alternatives as to the relevant project.
Id., at 227; see
Vermont Yankee, 435 U. S., at 551, 555. Because an EIS
is only one input into an agency’s decision and does not itself
require any particular substantive outcome, the adequacy of an EIS
is relevant only to the question of whether an agency’s final
decision (here, to approve the railroad) was reasonably
explained.
In short, when determining whether an agency’s
EIS complied with NEPA, a court should afford substantial deference
to the agency.
In practice, judicial deference in NEPA cases
can take several forms. For example, NEPA says that the EIS should
be “detailed.” 42 U. S. C. §4332(2)(C). Of course, the
meaning of “detailed” is a question of law to be decided by a
court.
Loper Bright, 603 U. S., at 391–392. But what
details need to be included in any given EIS? For the most part,
that question does not turn on the meaning of “detailed”—instead,
it “involves primarily issues of fact.”
Marsh, 490
U. S., at 377. The agency is better equipped to assess what
facts are relevant to the agency’s own decision than a court is. As
a result, “agencies determine whether
and to what extent to
prepare an EIS based on the usefulness of any new potential
information to the decisionmaking process.”
Public Citizen,
541 U. S., at 767 (emphasis added). So the question of whether
a particular report is detailed enough in a particular case itself
requires the exercise of agency discretion—which should not be
excessively second-guessed by a court. Brevity should not be
mistaken for lack of detail. A relatively brief agency explanation
can be reasoned and detailed; an EIS need not meander on for
hundreds or thousands of pages. So courts should not insist on
length as a prerequisite for finding an EIS to be
detailed.[
3]
The EIS also must identify significant
environmental impacts and feasible alternatives. But there too, an
agency exercises substantial discretion. An agency must make
predictive and scientific judgments in assessing the relevant
impacts (what are the likely impacts; do they rise to the level of
“significant”?) and alternatives (what are the potential
alternatives; are they really “feasible”?). As this Court has said,
“the term ‘alternatives’ is not self-defining,” and “[c]ommon
sense” should be brought to bear.
Vermont Yankee, 435
U. S., at 551. Black-letter administrative law instructs that
when an agency makes those kinds of speculative assessments or
predictive or scientific judgments, and decides what qualifies as
significant or feasible or the like, a reviewing court must be at
its “most deferential.”
Baltimore Gas & Elec., 462
U. S., at 103; see
Marsh, 490 U. S., at 378;
State Farm, 463 U. S., at 43.
In preparing an EIS, an agency also must
determine the scope of the environmental effects that it will
address. The textual focus of NEPA is the “proposed action”—that
is, the project at hand. 42 U. S. C. §4332(2)(C) (2018).
The agency therefore will obviously seek to assess significant
effects from the project at issue. But how far will the agency go
in considering the indirect effects that might occur outside the
area of the immediate project—for example, due to emissions or run
off from the project carried elsewhere by air or water? And will
the agency evaluate the environmental effects from other future or
geographically separate projects that may be initiated (or
expanded) as a result of or in the wake of the current project? And
what if another agency also possesses regulatory authority over a
related project?
In analyzing those scope questions, it is
critical to disaggregate the agency’s role from the court’s role.
So long as the EIS addresses environmental effects from the project
at issue, courts should defer to agencies’ decisions about where to
draw the line—including (i) how far to go in considering indirect
environmental effects from the project at hand and (ii) whether to
analyze environmental effects from other projects separate in time
or place from the project at hand. On those kinds of questions, as
this Court has often said, agencies possess discretion and must
have broad latitude to draw a “manageable line.”
Public
Citizen, 541 U. S., at 767 (quoting
Metropolitan Edison
Co. v.
People Against Nuclear Energy,
460 U.S.
766, 774, n. 7 (1983)).
To tie all of this together: When assessing
significant environmental effects and feasible alternatives for
purposes of NEPA, an agency will invariably make a series of
fact-dependent, context-specific, and policy-laden choices about
the depth and breadth of its inquiry—and also about the length,
content, and level of detail of the resulting EIS. Courts should
afford substantial deference and should not micromanage those
agency choices so long as they fall within a broad zone of
reasonableness. As the Court has emphasized on several occasions,
and we doubly underscore again today, “inherent in NEPA
. . . is a ‘rule of reason,’ which ensures that agencies
determine whether and to what extent to prepare an EIS based on the
usefulness of any new potential information to the decisionmaking
process.”
Public Citizen, 541 U. S., at 767. A
reviewing court may not “substitute its judgment for that of the
agency as to the environmental consequences of its actions.”
Kleppe, 427 U. S., at 410, n. 21.
Some courts have strayed and not applied NEPA
with the level of deference demanded by the statutory text and this
Court’s cases. Those decisions have instead engaged in overly
intrusive (and unpredictable) review in NEPA cases. Those rulings
have slowed down or blocked many projects and, in turn, caused
litigation-averse agencies to take ever more time and to prepare
ever longer EISs for future projects.
The upshot: NEPA has transformed from a modest
procedural requirement into a blunt and haphazard tool employed by
project opponents (who may not always be entirely motivated by
concern for the environment) to try to stop or at least slow down
new infrastructure and construction projects. Some project
opponents have invoked NEPA and sought to enlist the courts in
blocking or delaying even those projects that otherwise comply with
all relevant substantive environmental laws. Indeed, certain
project opponents have relied on NEPA to fight even clean-energy
projects—from wind farms to hydroelectric dams, from solar farms to
geothermal wells. See,
e.g., Brief for Chamber of Commerce
of the United States of America, et al. as
Amici Curiae
19–20.
All of that has led to more agency analysis of
separate projects, more consideration of attenuated effects, more
exploration of alternatives to proposed agency action, more
speculation and consultation and estimation and litigation. Delay
upon delay, so much so that the process sometimes seems to
“borde[r] on the Kafkaesque.”
Vermont Yankee, 435
U. S., at 557. Fewer projects make it to the finish line.
Indeed, fewer projects make it to the starting line. Those that
survive often end up costing much more than is anticipated or
necessary, both for the agency preparing the EIS and for the
builder of the project. And that in turn means fewer and more
expensive railroads, airports, wind turbines, transmission lines,
dams, housing developments, highways, bridges, subways, stadiums,
arenas, data centers, and the like. And that also means fewer jobs,
as new projects become difficult to finance and build in a timely
fashion.
A 1970 legislative acorn has grown over the
years into a judicial oak that has hindered infrastructure
development “under the guise” of just a little more process.
Id., at 558. A course correction of sorts is appropriate to
bring judicial review under NEPA back in line with the statutory
text and common sense.
Id., at 525. Congress did not design
NEPA for
judges to hamstring new infrastructure and
construction projects. On the contrary, as this Court has stressed,
courts should and “must defer to ‘the informed discretion of the
responsible federal agencies.’ ”
Marsh, 490 U. S.,
at 377.
Critically, as the Government and the Coalition
explained at oral argument, courts not only must defer to the
agency’s reasonable choices regarding the scope and contents of the
EIS, but also must keep in mind that review of an agency’s EIS is
not the same thing as review of the agency’s final decision
concerning the project. See Tr. of Oral Arg. 31–32, 70–71. That,
too, follows from NEPA’s status as a purely procedural statute. The
ultimate question is not whether an EIS in and of itself is
inadequate, but whether the agency’s final decision was reasonable
and reasonably explained. Review of an EIS is only one component of
that analysis. Even if an EIS falls short in some respects, that
deficiency may not necessarily require a court to vacate the
agency’s ultimate approval of a project, at least absent reason to
believe that the agency might disapprove the project if it added
more to the EIS. Cf. 5 U. S. C. §706. For example, in a
case like this one, even if the EIS drew the line on the effects of
separate upstream or downstream projects too narrowly, that mistake
would not necessarily require a court to vacate the agency’s
approval of the railroad project. Cf.
Vermont Yankee, 435
U. S., at 558.[
4]
In other words, as this Court has said before,
NEPA does not authorize a court to “ ‘interject itself within
the area of discretion . . . as to the choice of the
action to be taken’ ” by the agency.
Strycker’s Bay
Neighborhood Council, 444 U. S., at 227–228 (quoting
Kleppe, 427 U. S., at 410, n. 21). NEPA’s
procedural mandate helps “to insure a fully informed and
well-considered decision, not necessarily a decision the judges of
the Court of Appeals or this Court would have reached had they been
members of the decisionmaking unit of the agency.”
Vermont
Yankee, 435 U. S., at 558.
The “role of a court in reviewing the
sufficiency of an agency’s consideration of environmental factors
is a limited one.”
Id., at 555. The bedrock principle of
judicial review in NEPA cases can be stated in a word:
Deference.
B
Even apart from failing to afford sufficient
deference to the Surface Transportation Board, the D. C. Circuit’s
decision was mistaken on the merits under NEPA. The D. C.
Circuit erroneously required the Board to address environmental
effects from projects that are separate in time or place from the
88-mile railroad project at hand—that is, effects from potential
future projects or from geographically separate projects. Moreover,
those separate projects fall outside the Board’s authority and
would be initiated, if at all, by third parties.
In its EIS, the Board determined that upstream
oil drilling in the Uinta Basin and downstream oil refining along
the Gulf Coast were separate from the construction and operation of
the 88-mile railroad line. The Board’s EIS explained that the
“proposed rail line and any future oil and gas development projects
are not two phases of a single action,” but “separate, independent
projects.” App. 523. Those other projects, the Board reasoned,
should not be considered “part of the proposed action assessed in
the EIS.”
Ibid. The Board concluded that its EIS need not
evaluate the possible environmental effects from separate upstream
or downstream projects.[
5]
The Board’s approach complied with NEPA and this
Court’s longstanding NEPA precedents. Importantly, the textually
mandated focus of NEPA is the “proposed action”—that is, the
project at hand—not other future or geographically separate
projects that may be built (or expanded) as a result of or in the
wake of the immediate project under consideration. 42
U. S. C. §4332(2)(C) (2018); see
Aberdeen &
Rockfish R. Co. v.
Students Challenging Regulatory Agency
Procedures (SCRAP),
422 U.S.
289, 322–324 (1975);
Kleppe, 427 U. S., at 398–402.
Therefore, when the effects of an agency action arise from a
separate project—for example, a possible future project or one that
is geographically distinct from the project at hand—NEPA does not
require the agency to evaluate the effects of that separate
project.
To be clear, the environmental
effects of
the project at issue may fall within NEPA even if those
effects might extend outside the geographical territory of
the project or might materialize later in time—for example, run-off
into a river that flows many miles from the project and affects
fish populations elsewhere, or emissions that travel downwind and
predictably pollute other areas. Those so-called indirect effects
can sometimes fall within NEPA, as the Government explained at oral
argument. See Tr. of Oral Arg. 59–63.
But if the project at issue might lead to the
construction or increased use
of a separate project—for
example, a housing development that might someday be built near a
highway—the agency need not consider the environmental effects
of that separate project. To put it in legal terms, the
separate project breaks the chain of proximate causation between
the project at hand and the environmental effects of the separate
project. See
Public Citizen, 541 U. S., at 767 (citing
Metropolitan Edison, 460 U. S., at 774, and n. 7).
The effects from a separate project may be factually foreseeable,
but that does not mean that those effects are relevant to the
agency’s decisionmaking process or that it is reasonable to hold
the agency responsible for those effects. Cf.
Public
Citizen, 541 U. S., at 766–767. In those circumstances,
“the causal chain is too attenuated.”
Metropolitan Edison,
460 U. S., at 774. In other words, there is no
“ ‘reasonably close causal relationship’ ” between the
project at hand and the environmental effects of those other
projects.
Public Citizen, 541 U. S., at 767 (quoting
Metropolitan Edison, 460 U. S., at 774).
Moreover, and importantly, the Board here
possesses no regulatory authority over those separate projects. The
Board does not regulate oil drilling, oil wells, oil and gas
leases, or oil refineries. The Board approves railroad lines. See
49 U. S. C. §§10101, 10901. Other agencies possess
authority to regulate those separate projects and their
environmental effects. As this Court stated in one of the more
important sentences in the NEPA canon, “where an agency has no
ability to prevent a certain effect due to its limited statutory
authority over the relevant actions, the agency cannot be
considered a legally relevant ‘cause’ of the effect.”
Public
Citizen, 541 U. S., at 770. In other words, agencies are
not required to analyze the effects of projects over which they do
not exercise regulatory authority. For that reason as well, there
is no “ ‘reasonably close causal relationship’ ” between
the 88-mile railroad project at hand and the environmental effects
of the separate oil drilling and oil refining projects.
Id.,
at 767 (quoting
Metropolitan Edison, 460 U. S., at
774); see also
Robertson, 490 U. S., at 350–353;
Vermont Yankee, 435 U. S., at 550–551, 558.
To be sure, NEPA mandates that an agency
“consult with” other agencies as appropriate. 42 U. S. C.
§4332(2)(C). But there is a vast difference between, for example,
an agency’s consulting with the Forest Service to determine the
effects of a railroad line that would pass through a national
forest and an agency’s asking another agency to assess how 88 miles
of additional track in rural Utah would contribute to emissions or
climate change along the Gulf Coast. Indeed, “no rule of reason
worthy of that title would require an agency to prepare an EIS”
addressing effects from another project that is separate in time or
place from the project at hand—particularly when it would require
the agency to speculate about the effects of a separate project
that is outside its regulatory jurisdiction.
Public Citizen,
541 U. S., at 767–768 (citing
Aberdeen & Rockfish R.
Co., 422 U. S., at 325).
In this case, the Uinta Basin Railway was the
relevant project. NEPA therefore required the Board to consider the
environmental effects of that 88-mile railroad line’s construction
and operation. To the extent that the new 88-mile railroad line
could disrupt the habitat of protected species, or the new rail
embankments could cause soil erosion into local bodies of water, or
trains on the new line could pollute the air, NEPA dictated that
the Board evaluate those effects. And consistent with NEPA, the
Board here
did comprehensively evaluate those effects,
including via consultation with other agencies. As the D. C.
Circuit itself recognized, the Board explained that “construction
and operation of the Railway” would affect “water resources, air
quality, [and] special status species like the greater
sage-grouse.” 82 F. 4th, at 1168. But nothing in NEPA required
the Board to go further and study environmental impacts from
upstream or downstream projects separate in time or place from the
88-mile railroad line’s construction and operation.
Under NEPA, it also bears emphasis, a mere
“ ‘but for’ causal relationship is insufficient to make an
agency responsible for a particular effect.”
Public Citizen,
541 U. S., at 767. Likewise, the fact that other projects
might foreseeably be built or expanded in the wake of the current
project does not, by itself, make the agency responsible for
addressing the environmental effects of those other projects. The
agency may draw what it reasonably concludes is a
“ ‘manageable line’ ”—one that encompasses the effects of
the project at hand, but not the effects of projects separate in
time or place.
Ibid. (quoting
Metropolitan Edison,
460 U. S., at 774, n. 7). True, a new airport may someday
lead to a new stretch of highway; a new pipeline to a new power
plant; a new housing development to a new subway stop. But the
environmental effects of the project at hand constitute NEPA’s
textual focus. An agency need not assess the environmental effects
of other separate projects simply because those projects (and
effects) might not materialize but for the project at hand, or are
in some sense foreseeable.
Simply stated, a court may not invoke but-for
causation or mere foreseeability to order agency analysis of the
effects of every project that might somehow or someday follow from
the current project. See
Public Citizen, 541 U. S., at
767–768;
Metropolitan Edison, 460 U. S., at 774–775.
NEPA calls for the agency to focus on the environmental effects of
the project itself, not on the potential environmental effects of
future or geographically separate projects. A relatively modest
infrastructure project should not be turned into a scapegoat for
everything that ensues from upstream oil drilling to downstream
refinery emissions. As Justice Rehnquist underscored in
Vermont
Yankee, NEPA is not a “game” where project objectors can engage
in “unjustified obstructionism”—here, for example, by raising a
slew of remote effects that they think “ ‘ought to be’
considered.” 435 U. S., at 553–554.
To be sure, in certain circumstances, other
projects may be interrelated and close in time and place to the
project at hand—a residential development next door to and built at
the same time as a ski resort, for example. See,
e.
g.,
Robertson, 490 U. S., at 338–340.
The question then is whether that is a single project within the
authority of the agency in question. There may be a gray area in
defining the project at hand. Even in those circumstances, however,
a court’s review still must remain deferential, as we explained in
Part II–A above. In other words, even if the reviewing court in
such a case might think that NEPA would support drawing a different
line, a court should defer to an agency so long as the agency drew
a reasonable and “ ‘manageable line.’ ”
Public
Citizen, 541 U. S., at 767 (quoting
Metropolitan
Edison, 460 U. S., at 774, n. 7). All of that is to
again underscore that a difference may exist between what an agency
should do as a matter of good policy and best practices under NEPA,
and what a reviewing court may subsequently order an agency to do
under NEPA.
In this case, in any event, the NEPA question is
not close. The Board did not need to evaluate potential
environmental impacts of the separate upstream and downstream
projects. As to other projects upstream, the EIS rightly explained
that the environmental consequences of future oil drilling in the
Basin are distinct from construction and operation of the railroad
line. App. 525–527. As for other projects downstream, the Board
likewise correctly explained that any environmental effects from
highly regulated oil refineries along the Gulf Coast are well
outside the scope of the 88-mile railroad project in rural Utah.
Id., at 420–423, 539–542.[
6]
An agency may decline to evaluate environmental
effects from separate projects upstream or downstream from the
project at issue.
Public Citizen, 541 U. S., at 770.
Here, the Board’s EIS concluded that the “proposed rail line and
any future oil and gas development projects are not two phases of a
single action,” but “separate, independent projects.” App. 523. So
the Board concluded that they need not be considered “part of the
proposed action assessed in the EIS.”
Ibid. Absolutely
correct.
* * *
In deciding cases involving the American
economy, courts should strive, where possible, for clarity and
predictability. Some courts’ NEPA decisions have fallen short of
that objective. The proper judicial approach for NEPA cases is
straightforward: Courts should review an agency’s EIS to check that
it addresses the environmental effects of the project at hand. The
EIS need not address the effects of separate projects. In
conducting that review, courts should afford substantial deference
to the agency as to the scope and contents of the EIS.
Plaintiffs’ policy objections to this 88-mile
Utah railroad may or may not be persuasive. But neither “the
language nor the history of NEPA suggests that it was intended to
give citizens a general opportunity to air their policy objections
to proposed federal actions. The political process, and not NEPA,
provides the appropriate forum in which to air policy
disagreements.”
Metropolitan Edison, 460 U. S., at 777.
Citizens may not enlist the federal courts, “under the guise of
judicial review” of agency compliance with NEPA, to delay or block
agency projects based on the environmental effects of other
projects separate from the project at hand.
Vermont Yankee,
435 U. S., at 558.
We reverse the judgment of the Court of Appeals
and remand the case for further proceedings consistent with this
opinion.
It is so ordered.
Justice Gorsuch took no part in the
consideration or decision of this case.