On petition for writ of certiorari to the United States Court of
Appeals for the Third Circuit.
The petition for a writ of certiorari is denied.
Justice REHNQUIST, with whom THE CHIEF JUSTICE and Justice
POWELL join, dissenting.
In this case the Court of Appeals for the Third Circuit held
that a private party seeking to compel agency compliance with the
National Environmental Policy Act of 1969 (NEPA), 83 Stat. 852, 42
U.S.C. 4321 et seq., need not exhaust administrative remedies prior
to filing suit in Federal District Court. Because I believe that a
long series of our cases heretofore regarded as settled law require
such exhaustion, e. g., Myers v. Bethlehem Shipbuilding Corp.,
303 U.S. 41 (
1938), I dissent from the denial of the petition for certiorari and
would set the case for argument.
The case arises out of the effort of the Nuclear Regulatory
Page 449 U.S.
1096 , 1097
Commission and petitioners, the owners and operators of Three
Mile Island Nuclear Station, to treat and eventually dispose of
radioactive wastewater resulting from the respondents commenced
this action against the Commission and petitioners, alleging that
the Commission had approved petitioners' construction and operation
of a facility to decontaminate the radioactive wastewater, known as
EPICOR II, and planned to allow the processed water to be
discharged in the Susquehanna River. Specifically, respondents
alleged that the Commission had failed to prepare an environmental
impact statement for the EPICOR II system, in violation of NEPA, 42
U.S.C. 4332, and had failed to require petitioners to secure a
license or construction permit for the system, in violation of the
Atomic Energy Act of 1954, 68 Stat. 919, as amended, 42 U.S.C. 2011
et seq. The complaint also charged that the possible discharge of
"high-level radioactive" water into the river would violate both
the Federal Water Pollution Control Act (FWPCA), 301(f), 86 Stat.
846, 33 U.S.C. 1311(f), and a federal constitutional right to "be
born and to live mentally and physically unimpaired."
The District Court found that respondents had failed to exhaust
their administrative remedies under the Atomic Energy Act and
dismissed the complaint for lack of subject-matter jurisdiction. It
noted that the administrative remedy available under the Act, 10
CFR 2.206 (1980),1 " allows
Page 449 U.S.
1096 , 1098
plaintiffs to ask the [Commission] for all the relief sought in
this court ." It further noted that the Act makes any final
decision of the Commission reviewable exclusively in the courts of
appeals. 42 U.S.C. 2239(b) and 28 U.S.C. 2342.
The Court of Appeals affirmed in part and reversed in part.
Although it affirmed the District Court's dismissal of claims
arising under the Atomic Energy Act on the grounds that the
Commission has exclusive jurisdiction over licensing actions, 42
U.S.C. 2239(b), and that private parties may not judicially enforce
the Act, 42 U.S.C. 2271(c), it nonetheless found that the District
Court had jurisdiction to compel Commission compliance with NEPA.
It reasoned that where the Commission " fragments" its
environmental review of projects, as is allegedly the case here,
the district courts could prohibit such fragmentation. The court
went on to hold that the District Court had jurisdiction over
respondents' FWPCA and constitutional claims, reasoning that
respondents had satisfied the conditions of the FWPCA's
citizen-suit provision, 33 U.S.C. 1365(a), and that the District
Court was the "appropriate" forum to consider the constitutional
claims.
Petitioners contend, correctly in my view, that the decision
below ignored the "long settled rule of judicial administration
that no one is entitled to judicial relief for a supposed or
threatened injury until the prescribed administrative remedy has
been exhausted." Myers v. Bethlehem Shipbuilding Corp., supra, at
50-51-464; McKart v. United States,
395 U.S. 185, 193, 195,
1662, 1663d 194 (1969). Even the Solicitor General, who does not
seek certiorari in this case, "agrees with petitioners that the
[C]ourt of [A]ppeals erred in a number of its rulings and that its
decision is contrary to the prior decisions of this Court."
Memorandum for United States Nuclear Regulatory Commission 1.
Page 449 U.S.
1096 , 1099
The gist of petitioners' argument is that Congress has placed
with the Commission the authority to regulate its licensees'
handling of radioactive materials and has limited judicial review
of the Commission's decisions to the courts of appeals. This Court
has recognized that the adequacy of Commission compliance with
NEPA, not just with the Atomic Energy Act, is reviewable solely in
the courts of appeals pursuant to 42 U. S.C. 2239(b) and 28 U.S.C.
2342. See Vermont Yankee Nuclear Power Corp. v. NRDC,
435 U.S. 519, 526-527,
1203 ( 1978). Indeed, the decision below is in direct conflict with
a decision of the Court of Appeals for the District of Columbia
Circuit which held that where a statutory review procedure assigns
to the courts of appeals exclusive review responsibility over
agency action-as does the Atomic Energy Act-a district court may
not exercise concurrent jurisdiction to resolve allegations of
agency noncompliance with NEPA. City of Rochester v. Bond, 195
U.S.App.D.C. 345, 354-355,
603 F.2d
927, 936-937 (1979).
The "fragmentation" of judicial review in this case results not
from the action of the Commission, but from the decision below
which splinters judicial review of claims that arise essentially
out of the same factual setting. It is anomalous to hold, as did
the court below, that the Atomic Energy Act claims are reviewable
exclusively in the court of appeals, while claims arising under
NEPA, FWPCA, and the Constitution are reviewable originally in the
District Court. [
Footnote 2]
The
Page 449 U.S.
1096 , 1100
decision below means that the District Court, the Court of
Appeals, and the Commission will all exercise concurrent
jurisdiction over the same claims at the same time. Such a
trifurcated review procedure is not only inefficient, duplicating
judicial and administrative effort, but more importantly, it leads
to premature interference with agency processes, contrary to the
policy underlying direct review statutes. [
Footnote 3]
Although the Solicitor General concedes that the decision below
was wrong, he asserts that the case is not worthy of this Court's
attention because the decision will be regarded merely as an
"anomaly that cannot be reconciled with this Court's settled
teaching on exhaustion of administrative remedies." Memorandum for
United States Nuclear Regulatory Commission 5. I am not so
sanguine. I fear that unless accorded plenary review here the
decision below will spawn
Page 449 U.S.
1096 , 1101
others like it allowing circumvention of agency review and
pursuit of NEPA claims directly in the district courts.
Accordingly, I dissent from the denial of the petition for
certiorari.
Footnotes
Footnote 1 Title 10 CFR
2.206 (1980) provides in relevant part:
"(a) Any person may file a request
for the Director of Nuclear Reactor Regulation . . . to institute a
proceeding . . . to modify, suspend or revoke a license, or for
such other action as may be proper . . . .
"(b) Within a reasonable time after a
request pursuant to paragraph ( a) of this section has been
received, the Director . . . shall either institute the requested
proceeding in accordance with the subpart or shall advise the
person who made the request in writing that no proceeding will be
instituted in whole or in part, with respect to his request, and
the reasons therefor."
Footnote 2 Although it is
clear that the court below erred with respect to the NEPA claim, I
suggest that it is on no firmer footing with respect to the FWPCA
and constitutional claims. It appears, for example, that the
Commission has exclusive jurisdiction to regulate the discharge of
the type of radioactive water involved in this case, see Train v.
Colorado Public Interest Research Group,
426 U.S. 1, 16-17, 1945
(1976). In any event, all of the claimed violations arise out of
the very activities which are subject to Commission regulatory
control, and considerations of judicial economy require that all of
the claims be resolved in the first instance by the Commission.
Footnote 3 The problems of
segregated review are amply illustrated by the facts of this case.
On May 25, 1979, the same day suit was filed in this case, the
Commission issued a statement prohibiting the treatment or
discharge of contaminated water until it had completed an
environmental assessment. During the next several months, the
Commission staff prepared an environmental assessment on the
proposed operation of EPICOR II. The Commission eventually
published a draft Environmental Impact Statement, 45 Fed.Reg. 54495
(1980), and issued an opinion on October 16, 1980, permitting the
processing of radioactive wastewater by EPICOR II, but specifically
prohibiting any discharge of the processed water pending further
study. Respondents subsequently filed a petition for review of that
order in the Court of Appeals for the Third Circuit pursuant to 42
U. S.C. 2239. That case raises the same NEPA issues presented in
this case . Thus, the District Court, the Court of the Appeals for
the Third Circuit, and the Commission are presently exercising
concurrent jurisdiction over the same issues. This sort of
procedural chaos is invited by the decision of the Court of Appeals
in this case.
What may well be the better course both legally and practically
is suggested by a recent case in the District Court for the
District of Columbia which raised virtually the same issues
presented here. City of Lancaster v. NRC, No. 79-1368. There the
court dismissed with prejudice plaintiffs' suit on the basis, inter
alia, of the Commission's adherence to its May 25, 1979,
statement.